Monday, 16 January 2012

Update week 2

Forgot to post last week, didn't check my project schedule so i got a bit behind. Tried to make it up tho. Haven't really got any work to post as of yet since I'm still in the research phase, however i will put up my schedule. I've been told it's not very clear so maybe i can describe how it works and my reasoning on here.


Project schedule


Pre-Semester Work

- Create document structure.
- Begin research on artists and their creative methods.

January
-7th- Research environments.
-8th- Research environments.
-9th- Research cultures, update blog.
-14th- Research cultures, research religions.
-15th- Research cultures, research religions.
-16th- Research animals and creatures, update blog.
-21st- Research animals and creatures, reference drawing.
-22nd- Research animals and creatures, reference drawing.
-23rd- Research animals and creatures, reference drawing.
-28th- Thumbnail drawings based on research and reference drawings.
-29th- Thumbnail drawings based on research and reference drawings.
-30th- Thumbnail drawings based on research and reference research, update blog.


February
-4th- Thumbnail drawings based on research and reference research.
-5th- Thumbnail drawings based on research and reference research.
-6th- Thumbnails and first race initial designs, Update blog.
-11th- First race initial designs
-12th- First race initial designs
-13th- First race initial designs, update blog.
-18th- Second race initial designs
-19th- Second race initial designs
-20th- Second race initial designs, update blog.
-25th- First race design development
-26th- First race design development
-27th- First race design development, update blog.

March
-3rd- Second race design development.
-4th- Second race design development.
-5th- Second race design development, update blog
-10th- Design development, flesh out design for finalisation.
-11th- Design development, flesh out design for finalisation.
-12th- Design development, flesh out design for finalisation, update blog.
-17th- Finalise race designs.
-18th- Finalise race designs.
-19th- Finalise race designs, update blog
-24th- Polish time.
-25th- Polish time.
-26th- Stage 2 Hand in.
-31st- Evaluative report.

April
-1st- Evaluative report.
-2nd- Evaluative report.
-7th- Evaluative report.
-8th- Evaluative report.
-9th- Evaluative report.
-14th- Evaluative report.
-15th- Evaluative report.
-16th- Evaluative report hand in.


The aim is too update the blog every Monday after I've done my work. I chose to work in this pattern as to keep my research fresh in my mind and to transition from research to observational sketches to inital design sketches so to carry across the influences.  

No comments:

Post a Comment